KGHM Polska Miedź SA/ Głogów CHP
General Contractorship
Implementation years: 2011-2013
Turnkey construction in the General Contractor system of new Gas and Steam Unit at Głogów and Polkowice Power Plants
Subject of the contract:
Turnkey construction in the General Contractor system of the new Gas and Steam Unit with electric power under ISO: approx. 45 MWe
- thermal power: approx. 40 MWt
- gas-fired: (GZ 41,5)
- at: KGHM Polska Miedź SA in Głogów,on site of Huta Miedzi Głogów EC-3 Głogów.
Gas and Steam Unit will be a separate, complete power energy facility equipped with all systems
and circuits necessary to its proper operation, with technologial connections to external facilities
in scope of:
- heating output system
- electricity output system
- auxiliary steam input system
- heating water input system for own needs
- water supply
- sewage discharge
- teletechnical installations
- other necessary systems and technological installationsnecessary for proper functioning of the Gas and Steam Unit.
In connection with the accepted formula of the turnkey construction contract under General Contractor system, scope of the contract includes:
- all the design, engineering works
- all the construction and assembly works
- all the deliveries and services except for the ones defined in the Excemptions to the subject of the contract that are indispensableso that Gas and Steam Unit reaches the required operating characteristics Guaranteed Technical Specifications
- operating capacity and safety, even if such elements of construction works, deliveries and services are not specified in the contract.