PKE SA Elektrownia Łaziska
Delivery of:
spare parts to OP-650k boiler, turbo generator no. 12 at PKE SA Elektrownia Łaziska
Part I Delivery of 2nd live steam superheater, wall part.
Part IV Delivery of outlet chamber, 1st live steam superheater. -
Koksownia Przyjaźń Sp. z o.o. Dąbrowa Górnicza
Customer: Koksownia Przyjaźń Sp. z o.o. Dąbrowa Górnicza
Implementation year: 2010
Preparation of documentation and repair of pressure part of boiler no. 5, coke dry quenching installation
Subject of repair was: heat recovery steam generator with the following parameters:- nominal steam production 25Mg/h
- superheated steam pressure 3,9 Mg/h
- circulation gas flow 80 000 m3/h
- gas temperature at the 800° C
- outlet to the boiler
- feedwater temperature 102° C
- at the inlet to the heater steam temperature 120-440° C at the outlet of the boiler
Scope of repair was:
development and coordination with Office of Technical Inspection on boiler repair documentation:
- repair technology documentation
- boiler elements documentation subject to replacement including the necessary calculations
manufacturing and replacement of boiler pressure elements:
- I/II degree evaporator packages
- I steam heater packages
Works were carried out in 2nd gas-dangerous zone, in the immediate vicinity of active pipelines and equipment.
-
Fortum Częstochowa SA
Customer: Fortum Częstochowa SA
Implementation years: 2009-2010
Complex assembly works within CHP construction, Częstochowa
Scope of work included: Assembly of devices, pumps, coolers Modernisation of existing Rejtan heating plant
Offsite fabrication and assembly of process line pipings:- live steam pipelines
- feedwater pipelines
- demineralised water pipelines
- ignition oil pipelines
- air pipelines, Control and Measurement Instruments and Automation.
- glycol pipelines
- arterial condensate pipelines